Skip to main content
sociable systems.
Arc companion

The Question the File Was Never Asked

Nothing was hidden. The figures were not withheld; they were not yet due, and the due date fell after the decision they were material to. Written for the general reader, on what a building gets asked and what this facility class does not.

The question the file was never asked

When Cape Town's Municipal Planning Tribunal approved the King Air Industria land-use application on 14 July, the vote was four to one, and the member who dissented did so because the application lacked information. Asked how much water the thttps://www.dailymaverick.co.za/article/2026-07-14-two-giant-data-centres-secure-initial-green-light-from-cape-town-municipal-tribunal/wo facilities would use, the answer on the public record was that this would be confirmed after approval.

Five civil society organisations put that sequence in front of the South African Human Rights Commission on 24 August, asking for a national inquiry, an independent cost and benefit assessment, a pause, and an independent monitoring panel. Every one of those asks is reasonable. The framing that has grown around them is that something was hidden, and that framing is going to cost the people making it, because it is the one claim in this file that does not survive contact with the record.

Nothing was hidden. There is no embargoed annexure, no litigation about commercial sensitivity, no official who declined to answer. The figures were not withheld. They were not yet due, and the due date falls after the decision they were material to.

That is a stranger problem than concealment, and a harder one to fix.

What a building gets asked

South Africa has spent thirty years building an assessment culture. Mines, highways, power stations, harbours and wind farms arrive with specialist studies, public participation, and a paper trail of who gains and who carries the cost. Social impact assessment is a mature discipline in this country, with practitioners who have handled smelters, highways and resettlement programmes. On the hyperscale data centre file it is absent, and its absence is not an oversight by anyone involved.

The reason sits earlier than anyone's report, in a decision nobody experienced as a decision. A hyperscale data centre is industrial plant: a twenty-four-hour load carrying a contractual promise of near-perfect uptime, and that promise is diesel generators, fuel storage, a switching station, and a cooling choice that either draws on the same municipal system households draw on or does not. On the file it is frequently none of those things. It is a use reallocated inside industrial and warehouse rights that already exist, so no new heavy-industrial permit is sought, because none is required.

The national environmental instrument still bites, and it bites on the generators and the fuel. That produces a competent, properly conducted assessment of the diesel tanks. It does not produce an assessment of the facility.

So when the land-use tribunal asks its questions, it asks them correctly. Compatibility with the zoning scheme. Traffic relative to the prior permitted use. Heritage and biodiversity against the overlays. Every finding is true. A hostile reviewer reading that report finds no error, because there is none in it. What the facility will draw from the municipal system is not a land-use compatibility question, so it goes to the design stage, where engineers check it against engineering standards and it passes, because meeting engineering standards is what a competent design submission does.

The classification was the assessment. Everything downstream inherited a question set that was fixed before any specialist opened a file.

The part with no owner at all

There is a second gap underneath, and it is the one that will matter in five years.

These facilities arrive in increments. A hall, then another hall, then a substation, each slice individually modest. The campus is not modest. And where several such campuses draw on one municipal system, no process in the sequence adds up the column. Each application is adjudicated on its own site, correctly, by people doing their jobs properly. The total belongs to no door, no tribunal and no register. Reporting on the Cape Town pipeline alone puts it at 34 per cent of the city's current electricity supply, a figure assembled by journalists because no public process assembles it.

This is not a compliance failure anyone can be prosecuted for. That is precisely why it will not fix itself.

What the pausing jurisdictions actually did

The international comparators are more encouraging than the sector's critics allow and less comfortable than its defenders hope.

Singapore ran a de facto moratorium on new large-scale approvals from 2019, lifted it in 2022, and reopened through a competitive call for applications rather than a queue, with efficiency and sustainability criteria attached and a capacity band per applicant. Roughly eighty megawatts went to four operators.

Ireland's energy regulator ran its own de facto connection moratorium from 2021 and published a final policy in December 2025 reopening the grid on terms that had not previously existed. Anything above ten megavolt-amperes must now bring its own dispatchable generation or storage sized to its connection, site itself where the grid is unconstrained, and match four fifths of its annual demand with renewable investment in Ireland.

New South Wales did something sharper still, and it did it twelve days ago. On 17 August it released a bespoke data centre policy framework, the first in Australia, resting on six performance principles: environmental and efficiency standards, no net cost to consumers and communities, funding additional water and energy supply, local community infrastructure, supply-chain investment, and skills. Proponents who meet them receive a government commitment to assess the application within 75 days.

That last one is the instrument this conversation is missing. New South Wales did not choose between approving and refusing. It priced the conditions, and what it offered in exchange was speed. Several of these places remain exactly the global hubs they were trying to stay.

The cheaper version of this argument

An applicant reading the SAHRC submission will hear a demand to slow down. The more useful reading is that an approval built on an untested benefit claim is a fragile asset.

Benefit claims in this sector arrive at a level of abstraction that no number could attach to: jobs, skills transfer, downstream industries, catalytic growth. They are rarely false. They were simply never written in a form anyone agreed to test, and an unenforceable benefit is a forecast. The capital footprint of this plant is enormous and its permanent employment footprint is small and highly skilled, which is what the technology is rather than a moral failing of anyone who builds it. It becomes a public problem at one point only, when that reality is presented to a tribunal in a register calibrated for labour-intensive development.

The fix is smaller than an inquiry and available immediately. Ask what the facility will draw, before the decision that draw is material to. Assess the total across facilities sharing one system, because somebody has to hold that column. And attach falsification conditions to the benefit claims, in the conditions of consent, where a number can live.

The next application to arrive with those three things attached will be the most defensible one in the country, and it will have cost its applicant a fraction of what the first contested refusal costs somebody else.


Sources

Every claim above was checked against the document itself rather than a summary of it. The ones corrected after checking, including two of these comparators, are logged in the Verification Ledger.


Liezl Coetzee works on social performance and impact assessment for resource-intensive infrastructure. She writes Sociable Systems, a South African research and advisory practice working on AI governance, accountability and operational safety for high-stakes industries where digital failures have physical and human consequences, and maintains the SA Data Centre Register.